The challenge
The ballasted roof was leaking heavily over a newly remodeled interior, so replacement could not wait.
Because of COVID precautions and the data center environment, crews could not access the roof from inside the building.
The TEMA solution
TEMA used a single-contract design-build delivery to skip the traditional competitive bidding process and define the scope clearly from the start.
TEMA set up exterior scaffolding for all access and managed debris and cleanliness to protect sensitive equipment.
The result
The full replacement was completed within the two-month window, protecting the new interior before year end.
Project photos
More on our work with retail & office.